|
Hostmark Safe Routes to School Project
STATUS 5/9/12: Pre-construction |
The Hostmark Safe Routes to School Project will add sidewalks to the south side of Hostmark Street from SR 305 to Caldart. The construction will include new sidewalks, curb, gutter, new crosswalks and ADA ramps. The project will go out to add May 18, 2012 and have a bid opening of June 11, 2012. The project is funded by federal grants. |
Noll Road Roundabout
STATUS 5/9/12: Pre-construction |
| |
The design stage of the Noll Road Roundabout project is complete. The project will go out to add on May18, 2012 and have a bid opening of June 11, 2012. The proect is scheduled to begin on June 14, 2012 and be completed in early September. |
Sixth Avenue Improvements
STATUS 5/9/12: Design |
| |
The Preliminary design of the Sixth Avenue Improvements is currently underway. Several public meetings were held in the spring of 2012 where the project goals were identified. The Sixth Avenue Improvements will protect Liberty Bay water quality by treating stormwater runoff from 6th Avenue, Hostmark Street and Lincoln Road. Additionally, the project will improve pedestrian and bicycle safety by enhancing sidewalks, crosswalks and bike areas.
Sixth Avenue NE Traffic Calming Map
Sixth Avenue NE Traffic Calming Public Notice
|
Anderson Parkway
STATUS 5/9/12: Design |
| |
The preliminary design of Anderson Parkway is complete. The City has held several public meetings regarding the proposed improvement. One goal of the project is to protect Liberty Bay water quality by treating stormwater runoff from the parking lot. The project will also increase the capacity of the parking lot and replace deteriorated pavement which has reached the end of its useful life. Pedestrian and vehicle safety will be improved by enhancing walkways, visibility, improving vehicle flow and providing new lighting . The Anderson Parkway project is scheduled to begin in February of 2013.
Anderson Parkway Public Meeting Notice - March 19, 2012
Anderson Parkway LID Retrofit Public Notice
Anderson Parkway Map |
Fourth Avenue & Viewmont Improvements
STATUS 5/9/12: Complete |
| |
The City is currently installing new crosswalks and stop bars at the 3 way stop at 4th and Viewmont. Appropriate ADA ramps, sidewalk and drainage improvements will also be constructed. The improvements are intended to increase pedestrian safety and visibility.
|
Fjord Drive Slide Repair
STATUS 5/9/12: Complete |
| |
In late 2009, a landslide occurred on Fjord Drive that destabilized the road and forced the shutdown of the southbound lane to traffic. The City received a federal grant in addition to City funds to repair the slide.
A soil nail retaining wall was installed to stabilize the bank, road and surrounding infrastructure. A 350 foot section of Fjord was repaved and a new guardrail was installed. Fjord Drive is now open to all traffic.

|
|
Noll Road Improvements, Phase I
STATUS 10/26/11: Complete |
| |
The Noll Road Improvements are complete. Examples of Low Impact Development are present throughout the project corridor. There is a shared use path constructed of pervious asphalt that begins at Poulsbo Elementary School and continues to the entrance of Strawberry Fields. Pervious concrete sidewalks were used throughout the project and new asphalt was paved in appropriate locations. The new design includes striping for bicycle lanes and uses rain garden technology to manage storm water. This is the first project designed and constructed as part of the Noll Road Corridor Study and was funded by local street capital monies and federal grants. The City would like to thank the public for their patience with the Noll Road project. Total project cost: $750,000
 |
 |
Noll Road Improvements, Phase 1 Map |
| |
|
South Viking Avenue Improvements
STATUS 4/12/11: Complete, except a few outstanding work items |
| |
The South Viking Avenue Improvements project is complete. New sidewalks, a center turn lane, street lighting, bicycle lanes, full pavement restoration and landscaping were constructed as part of the project. The project was completed in two phases and funded by both state and federal grants. Total project cost - $1,500,000 |
 |
South Viking Avenue |
|
Mesford Improvements
STATUS 4/12/11: Complete |
| |
This project was completed in 2010 and included construction of a 9' wide sidewalk, paved parallel parking and new pavement on the existing road. Low Impact Development (LID) techniques were used to handle storm water, including pervious concrete and pervious asphalt. Storm water drains through these surfaces to naturally recharge groundwater and remove pollutants. Total project cost-$400,000. |
Before Construction Picture After Completion Picture |
|
|
6th Ave and 9th Ave Sewer Pumpstations
STATUS 4/12/11: Pre-design, construction scheduled for 2012 or 2013 |
| |
Two sewer pumpstations, one at 6th Avenue and one at 9th Avenue have reached the end of their useful life. These stations pumps sewerage up to the sewer main in Highway 305 and out to the treatment plant in Brownsville. The pumpstations are over 40 years old and must be replaced soon. The City has begun design on a project to replace these two pumpstations and replace the aging sewer infrastructure on Fjord Drive and a portion of 6th Avenue. A consultant was hired in February to start design on the project. Total project costs are not clear at this time and are highly dependent on the type of design chosen for the project. |
|
Liberty Bay Waterfront Trail
STATUS 4/12/11: Soliciting consultant proposals for design |
| |
The City is currently in the process of hiring a consultant to assist with design of the Liberty Bay Waterfront Trail project. This project will extend trails in American Legion Park to the existing trail system in Fish Park. The design phase of this project will being summer 2011. |
 |
Liberty Bay Waterfront Trail RFQ |
|
The following projects are being considered by the City or are in their preliminary design stages: |
| |
- Big Valley Water Transmission Main
- Third Avenue NE Improvements (Front Street to Iverson Street)
- Lincoln road Improvements (NE Laurie Vei Loop to Noll Road)
|